BOP installation of equipment, prefabrication and assembly of piping. Scope of work: Receipt, custody, storage and delivery of equipment and materials owned by ENEL, including raw materials and equipment needed for the new facility. Mechanical assembly, including handling, prefabrication, installation, testing, commissioning and start-up of the...

Characteristics: • Length (km): 89.6 • Diameter (in): 36” (914 mm) • Pressure (bar): 80 • Pipe: API5L Grade X-70   Principal details: • 6 valve positions • 2,200 m horizontal perforations 48” • 2,250,000 m³ of earth movements • 23,000 m³ concrete for protection • 2 automatic welding lines (6+3 cabins)   Automatic welding line Heavy earth moving...

The project consisted of the mechanical assembly of the new hydrocracker plant in the Cartagena refinery. Repsol supplied the equipment and piping and CPI Copisa Industrial supplied the auxiliary materials.   Scope of work: Custody, storage and installation of equipment. Brackets supply. Manufacture of brackets and piping...

The works consist of the prefabrication of piping, mechanical assembly of BOP (Balance of Plant) equipment, assembly of piping in the BOP and Power Island, thermal insulation and painting. The scope of the works involves the assembly of 392 tonnes of equipment, the prefabrication of...

The works consist of the prefabrication of piping, mechanical assembly of BOP (Balance of Plant) equipment, assembly of piping in the BOP and Power Island, thermal insulation and painting. The scope of the works involves the assembly of 392 tonnes of equipment, the prefabrication of...

The project developed in Mauritania, specifically in the Tasiast area, is part of the “Tasiast Optimization project”, which is an optimization and expansion project being carried out by the Canadian mining company through its Mauritanian subsidiary, Tasiat Mauritanie Limited, SA .   Main works: Construction of new facilities...