- New Terminal Area Control Centre (TACC) in Valencia, Spain. Solar and photovoltaic energy installation. (September 2008 – June 2011)
- Construction of the hydroelectric project at Puente Alba Mill on the Bernesga River, T. M. de La Robla, Leon, Spain. Civil works. (November 2011 – October 2014)
- Central Energy Building in Zona Franca, Barcelona, Spain. Civil Works. (June 2010 – January 2012)
- Remodelling of spaces in the offices of ACA (Catalan Water Agency), Barcelona, Spain. Solar panels installed on the roof. (September 2019 – January 2020)
- Renovation of the Hotel located in the Sant Josep building – Santuari de la Mare de Deu de Nuria, Girona, Spain. Geothermal Central Installation. (July 2007- November 2011)
- Urban spa in the “El Escaladillon” pavilion in Sallent de Gallego, Huesca, Spain. Solar panels installed on the roof. (July 2006 – June 2008)
- Hospice for families of children with cancer in Llars Mundet, Barcelona, Spain. Solar panels installed on the roof. (August 2009 – April 2010)
- AMMA Gerontological Centre Vilanova del Cami, Barcelona, Spain. Solar panels installed on the roof. (February 2005 – 2006)
- Juan Marse Library and Car Park, Barcelona, Spain. Solar panels installed on the roof. (November 2001 – February 2004)
- CEIP Renaixença – 1 Line – Els Hopstalets de Pierola, Barcelona, Spain. Solar panels installed on the roof. (May 2005 – January 2006)
- Actur nursery school in Zaragoza, Spain. Solar panels installed on the roof. (September 2006 – August 2007)
- Santa Isabel School in Zaragoza, Spain. Solar panels installed on the roof. (November 2006 – November 2007)
- Construction of a new building for the secondary school in Vilafranca del Penedés, Barcelona, Spain. Solar panels installed on the roof. (February 2017 – June 2018)
- Construction of a building with 54 homes, facilities and parking at Calle Lluis Borrassa 23, Barcelona, Spain. Photovoltaic panels installed and geothermal power plant. (November 2019 – October 2021)
- Construction of a building with 68 homes, 3 business premises and 69 parking spaces in L’Hospitalet de Llobregat, Barcelona, Spain. Photovoltaic panels installed on the roof. (June 2006 – November 2008)
- Construction of two blocks of homes, one with 24 homes and the other with 76 homes in Cornella de Llobregat, Barcelona, Spain. Solar panels installed. (May 2001 – June 2004)
- Construction of a building with 36 homes, business premises and car park at Avenida Meridiana 256, Barcelona, Spain. Solar panels installed on the roof. (March 2005 – November 2006)
- Construction of 88 subsidized housing, business premises and garage on Avenida Rey Juan Carlos and La Milagrosa, Jerez de la Frontera, Cádiz, Spain. Solar panels installed. (August 2008 – January 2010)
- Construction of 33 subsidised homes, 36 parking spaces, 3 storage rooms and 3 business premises in the Mas Pascual sector, Begues, Barcelona, Spain. Solar panels installed. (June 2008 – March 2010)
- Construction of 48 homes and car parks in the Can Coll sector, Torrellas de Llobregat, Barcelona, Spain. Photovoltaic panels installed on the roof. (October 2008 – June 2010)
- Construction of 64 subsidised homes under special arrangements for sales. El Rancho Industrial Park, plots 601 and 602. Moron de la Frontera, Seville, Spain. Solar panels installed on the roof. (October 2008 – June 2010)
- Construction of 76 homes on Avenida Blas Infante- Cerrofruto, Jerez de la Frontera, Cádiz, Spain. Solar panels installed on the roof. (August 2009 – October 2012)
- Construction of two buildings with 64 homes and a private car park on the R-2 and R-8 plots of the La Guinardera development in Sant Cugat del Valles, Barcelona, Spain. Solar panels installed on the roof. (September 2005 – April 2008)
- Construction of a building with 164 homes, car parks and facilities on Calle Camí Antic, Valencia, No. 96-116, Barcelona, Spain. Solar panels installed on the roof. (February 2006 – September 2008)
- Construction of the Regional Emergency Centre in Molinicos, Albacete, Spain. Solar panels installed. (August 2009 – March 2010)
- Construction of bus station and underground car park in Lloret de Mar, Girona, Spain. Photovoltaic panels installed on the roof. (March 2005 – May 2007)